Typical conflicts in IT projects
- Functions from the quotation are missing or work differently from what was described.
- The software is slow, unstable or has security vulnerabilities.
- After a migration, data is missing or interfaces no longer work.
- The service provider demands additional charges for work that, from your point of view, had been agreed.
- There is no documentation, and nobody apart from the service provider knows the system.
In all these cases, two points of view are pitted against each other. An independent technical review separates what can be established objectively from what remains a matter of interpretation.
How a project report examines
- Target state: what was agreed? The basis is the quotation, contract, specification, acceptance records and correspondence.
- Actual state: what was delivered? We check function, security, performance, data and documentation on the system itself.
- Comparison: every deviation is described, evidenced and classified technically – including against the generally accepted state of the art where nothing specific was agreed.
- Effort: what will it cost to remedy the defects or to complete the project?
Whether the findings give rise to any claims is for your legal adviser to judge. The expert report provides the technical basis for this – often it is already enough to reach an objective agreement with the service provider.
The documents you should collect
- Quotation, order or contract with all annexes
- Specification, requirements document or statement of work
- Invoices and quotations for additional work
- Acceptance records, notices of defects and the most important email correspondence
- Access to the system or a copy of the installation
The more complete the documents, the more precise the expert report – and the lower the effort. Anything that is missing, we name openly in the expert report.
What does a project report cost?
The effort depends mainly on the volume of documents and the number of questions. According to our guide values, a project report based on documents with around 80 pages of documents and four questions comes to just over 30 hours. You will find the guide values and worked examples under Costs of an IT expert report; before you commission us, you always receive your own estimate.
Frequently asked questions
Does the project have to be completed for an expert report?
No. An ongoing or abandoned project can also be assessed. An early look is often even cheaper, because undesirable developments can still be corrected.
Can you take over the project afterwards?
If you wish, yes – for example for websites, Microsoft 365 or a Linux migration. We tell you this openly before the expert report so that our independence remains transparent.
Can the expert report also be used in court?
It is a private expert report commissioned by you. How it is weighed in proceedings is decided by the court; your legal adviser will advise you on this. Our expert is an independent IT expert; Erdea Solutions prepares independent private expert reports (Privatgutachten) and does not hold an official appointment as an expert.
Have your project reviewed
Send us a short description – you receive an initial assessment and a cost estimate.
Topics
- IT Expert Reports & Preservation of Evidence
- IT expert report
- Project report
- Software defects
- Specification